Project Budget:
• Previous Budget $2,540,000
• Revised Budget $2,900,000
Budget increase due to
environmental permitting
regulatory requirements
Project Schedule:
• Construction Start Q2 2024
• Substantial Completion Q3 2024
Project Budget and Schedule
5