RCF 5th Floor Parking Membrane
Request Commission Authorization for Executive Director to:
• Advertise, award, and execute a major public works construction
contract for the 5
th
Floor Parking Membrane project
2
Project Purpose and Scope
Purpose:
To resurface the employee and visitor parking area located on the
5
th
Floor of the Consolidated Rental Car Facility (RCF)
Scope:
• Remove and replace the existing parking membrane
3
Project Location
4
Employee and Visitor
Parking Area
Rental Car
Facility
N
Project Budget & Schedule
5
Project Budget:
Original Budget: $11,417,000
Current Budget: $9,300,000
Key Schedule Milestones:
• Construction Start: Q2 2024
• In-Use Date: Q3 2024