Perimeter Access & Gate Enhancements
Perimeter Intrusion Detection System Phase 2
(CIP# C801363, C800844)
Seattle-Tacoma
International Airport
Item No. 8d_supp
Date of Meeting November 14, 2023
2024 Airfield Projects Contract 3
• Request Commission authorization for the ED to:
authorize final design and preparation of construction bid documents for
the Perimeter Access & Gate Enhancement (PAGE) project
advertise, award, and execute a major public works construction contract
for PAGE and Perimeter Intrusion Detection System (PIDS) Phase 2, and
transfer budget/authorization, as necessary, between the two Projects
procurement of long lead material items
include a Project Labor Agreement
2
2024 Airfield Projects Contract 3 Scope
• PAGE
Automate three Airport Operations Area (AOA) perimeter vehicle access
gates and install access control system, cameras and lighting;
Replace three 7’ gates with 12’ gates and upgrade some outdated
equipment at the gates;
Replace perimeter fence and signage to comply with Port standards;
Install razor wire on existing perimeter fence along the north and east AOA
perimeter.
• PIDS Phase 2
Install access control system to two AOA perimeter gates so that personnel
accessing the AOA area can be identified.
3
2024 Airfield Projects Schedule
4
Construction Contract # Contract #3
Commission design & construction
authorization
2023 Quarter 4
Construction start 2024 Quarter 3
In-use date 2024 Quarter 4
2023 Airfield Projects Budget
5
Cost Breakdown This Request Total Project
Perimeter Access and Gate Automation (C801363)
Design
$669,000 $953,000
Construction
$2,447,000 $2,447,000
Subtotal $3,116,000
$3,400,000
Perimeter Intrusion Detection System (C800844)
Design
$0 $3,025,000
Construction
$700,000
$23,044,000
Technology
$0 $8,145,000
Subtotal $700,000 $34,214,000
Total
$3,816,000 $37,614,000
Operated by the
Port of Seattle
FlySEA.org
Thank
You!
6