
COMMISSION AGENDA – Action Item No. __8h__ Page 8 of 9
Meeting Date: October 24, 2023
Template revised June 27, 2019 (Diversity in Contracting).
November 16, 2021 - The Commission authorized the Executive Director to (1) advertise and
execute a major works construction contract and (2) include a Project Labor Agreement for
the 2022 Airfield Pavement and Supporting Infrastructure Replacement Project, at the
Seattle-Tacoma International Airport. This authorization is for $24,000,000 with a total
authorized to date of $79,195,000 and a previously approved total 2021-2025 program
budget of $153,500,000.
August 10, 2021 – The Commission authorized the Executive Director to advertise and award
a major public works contract to replace the North Runway Protection Zone Culvert (NRPZ
Culvert), a year 2022 component of the 2021 to 2025 Airfield Pavement and Supporting
Infrastructure Replacement Program. This construction authorization is for $3,800,000 for a
total program authorization to date of $55,195,000. The total 2021-2025 program cost is
$153,500,000.
November 10, 2020 – The Commission authorized the Executive Director to (1) advertise and
execute a major works construction contract and (2) include a project labor agreement for
the replacement of distressed pavements and supporting infrastructure for the 2021 portion
of the 2021-2025 Airfield Pavement and Supporting Infrastructure Replacement Program at
the Seattle-Tacoma International Airport. This construction authorization is for $37,900,000
for a total authorization to date of $51,395,000. The total 2021-2025 program cost is
$153,500,000.
October 22, 2019 – The Commission authorized the Executive Director to authorize design
and preparation of construction documents for the 2021-2025 Airfield Pavement and
Supporting Infrastructure Replacement Projects at the Seattle-Tacoma International Airport
in the amount of $16,000,000 and approve the use of a project labor agreement (PLA) for
each year’s construction contract.
Airfield Utilities Infrastructure (AUI) (CIP C801177)
October 25, 2022 – The Commission authorized the Executive Director to (1) advertise,
execute two separate construction contracts, and transfer budget/authorization, as
necessary, among the 2023 Airfield Projects; (2) procure long lead items; (3) include a
Project Labor Agreement for both contracts; (4) authorize use of Port crews for abatement
work. The amount of this authorization request is $67,153,000. The total estimated cost for
all projects included in this authorization is $255,945,000.
August 10, 2021 – The Commission authorized the Executive Director to (1) complete design
and prepare construction documents for the Airfield Utilities Infrastructure (AUI) project at
Seattle-Tacoma International Airport (SEA) and (2) enter into reimbursable agreements with
the Federal Aviation Administration. This design authorization is for an amount of
$6,300,000 out of a total estimated project cost of $46,200,000.
Passenger Loading Bridge (PLB) Renewal and Replacement Phase 3 (CIP C801180)