• Scope: Provide funding and in-kind support for City-led tasks
• Role: Project partner
• Responsibilities:
– Funding for site characterization, design, permitting tasks (NTE $500k)
– In-kind support (NTE $50k)
• Staff: Provide subject matter expertise for permitting and habitat design
• Space: Duwamish River Community Hub for outreach, project meetings
• Materials: Contribution of large wood, plants, soil, mulch
• Future: Request for Phase 2, construction support ~$2m + ~$50k in-
kind support (under separate MOA or amendment)
6
MOA: Port of Seattle Role & Responsibilities
Note – City of Seattle estimates total project cost, including construction, to be approximately $15-20 m (City paying bulk of costs)