Telecommunication Meet Me Room (MMR)
Fiber Construction
Tyler Salisbury
AV PMG Capital Project
Manager
September 12 , 2023
Hein Mac
AV F&I Manager Engineer
Electrical
Item No. 8d_supp
Meeting Date: September 12, 2023
Project Overview
Establish new permanent telecommunication connection pathway into the Airport
Telephone services
Internet and Intranet
Wi-Fi connectivity and Office connections
Airport Reservation System and Airport Check-in System
Benefits:
Relocate legacy connections and upgrade from copper to high-speed fiber.
Bring new services and service providers into the Airport.
Provide connection redundancy and resiliency (Dual Pathway).
Request:
Authorization for construction of the fiber connections
This will fully authorize the Telecommunication Meet Me Room project
2
Project Scope - Fiber
Fiber Scope
Install fiber interconnections between
Service providers and Port equipment.
Install fiber in a primary pathway to each
Main Distribution Room (MDR).
Install fiber in a secondary pathway to
each MDR.
New tray and conduit pathways are required
to keep the connections separated.
3
Project Opportunities
Opportunity DESCRIPTION
Increased Resiliency The project has identified and will be installing a secondary pathway to
each MDR from the MMR. This will provide data redundancy and resiliency
to the airport which is not currently available with the legacy connections.
Diversity of services and
providers
The MMR will have space for new service providers to access the airport.
These providers can bring additional and competing services into the
airport.
Synergies with the Utility
Master Plan and future
capacity
This project aligns with recommendations in the Utility Master Plan for
increased resiliency and capacity for future growth.
4
Project Risks and Mitigation
RISK DESCRIPTION MITIGATION PLAN
Supply Chain - Fiber Availability of fiber cabling Identifying the long lead items in advance
and working with the contractor to put
orders in early.
5
Fiber Scope
Commission for construction authorization 3Q 2023
Construction Start 2Q 2024
Substantial Completion Fiber 4Q 2025
Schedule
6
Budget and Authorization
7
Authorization Amount Note
Previous authorization $13,703,00 September 2022
This Request $7,997,000 Fiber Construction Funding
Total Authorized $21,700,000 Building & Fiber fully authorized
Total Remaining $0
We are here
Cone of Certainty
8
Action Requested
Authorization to advertise, award, and execute a major works construction contract
to construct
Use of Port of Seattle Crews for design support and pre-construction activities
This request is to authorize $7.997M
Total authorization is $21.7M
This will fully authorize the Telecommunication Meet Me Room Project
9
Questions?