
COMMISSION AGENDA – Action Item No. 8d Page 5 of 5
Meeting Date: September 12, 2023
Template revised June 27, 2019 (Diversity in Contracting).
The project team underwent a detailed review of the various locations available to house legacy
and future connections. The location at the south end of the airport is near existing connection
points for both the Airport and Service Providers. The installation of fiber connections were
limited at this stage to the minimum needed for basic functionality. The addition fiber
connections for growth and to connect to additional MDRs were being considered for inclusion
in other telecommunication work.
In July 2019, the project team advertised a design build package that included the construction
of the building and the connection to the existing Airport infrastructure. That bid resulted in one
bid with a cost greater than 35% over the engineers estimate. The bid was reviewed, with some
line items removed. While the team began the process of returning to commission for additional
funding when the project was put on hold and the deferred project list during the COVID-19
workplace disruption.
In September 2021 the project efforts were restarted, and scope increased to be fully functional
by including the fiber required to connect to each MDR (3 in total), sufficient circuits to migrate
the legacy connections, and to establish the connection infrastructure within the MMR facility
for future growth from existing or new suppliers. Through the restarted efforts the secondary leg
was identified and included to improve the Airport’s data redundancy.
ATTACHMENTS TO THIS REQUEST
(1) Presentation slides
PREVIOUS COMMISSION ACTIONS OR BRIEFINGS
September 13, 2022 – The Commission authorized $2,000,000 and execute a design build
contract.
February 8, 2022 – The Commission authorized $7,725,000 for design and construction of the
MMR Building and authorized design of the MMR Fiber work project. Commission
authorization of the construction of the MMR fiber will be a future request.
September 26, 2017 – The Commission authorized $3,978,000 for design and construction.