COMMISSION AGENDA – Briefing Item No. 11a Page 2 of 4
Meeting Date: September 12, 2023
Template revised September 22, 2016.
UA project will be brought forward under the Airline Realignment umbrella, with the discrete
scopes of work separated under each project.
Currently, the Port anticipates completing the new operational ramp prior to the opening of the
new lounge on Concourse B. Presently, the UA project is tracking to request Commission
authorization for construction in Q2 2024 with a substantial completion in Q3 2025.
Description Contract Document Status
Package 1 Enabling Work Package
90% Complete now, Issue for Construction
Q4 2023
Package 2 Mechanical System Upgrades
60% Complete now, Issue for Construction
Q4 2023
Package 3
Concourse B Ramp Renovation
& Expansion
60% Complete now, Issue for Construction
Q4 2023
Package 4
Zone 4 Ticket Counter
Reconfiguration
60% Complete now, Issue for Construction
Q1 2024
TBD United Airlines Lounge
Design contract executed June 2023,
anticipate 30% complete by Q4 2023
Program Budget and Schedule
The 30% design development documents, with the enabling work package accelerated to 60%
design development, were delivered in April. This initiated an estimate and reconciliation of the
airline realignment scope, along with preparation of an independent cost estimate. The resulting
effort informed the revised estimate range of $102M to $140M, refined from projected range of
$98M - $172M previously shared with the Commission in February. Note that the costs being
carried for the United Airlines Lounge are from a conceptual estimate performed in December
2022. The project team is expecting revised budget estimates from UA in Q4 2023.
Since April 23, 2023, the project team, including the GCCM and its subcontractors, have been
evaluating the milestone schedule to identify areas for efficiency. The Electrical and Mechanical
subcontract trade partners contracted during preconstruction are now included in this effort to
inform the schedule updates based on their detailed understanding of the complex infrastructure
phasing required. This early engagement also includes coordination with Port stakeholders, and
jurisdictional authorities to ensure functional continuity with existing airport systems and
operations throughout the project’s phased construction.
Key Project Milestone Current Delivery Dates:
(1) United Airlines Gates to be allocated on Concourse B – September 2025
(2) United Airlines Lounge on Concourse B – Q4 2025