Procurement Risks
6
High
Medium
Low
Risk Probability Impact Mitigation
Required gangways manufacturing time:
ongoing global supply chain instability and
limited availability of some
materials/components may add significant time
to manufacturing schedule.
Expedite RFP and gangways vendor contract execution to
degree possible. Limit equipment features and extras to
degree possible to minimize manufacturing
requirements.
Gangways cost: Ongoing global economic
instability and cost inflation may result in
estimated cost escalation.
Expedite RFP and gangways vendor contract execution to
degree possible to limit cost escalation due to inflation.
Limit equipment features and extras to degree possible
to minimize costs.
Gangways transport time: Limited number of
qualified, and US located, gangways
manufacturers may require long distance global
transport for delivery to Terminal 91
Maximize potential number of vendors by limiting
specialized gangways requirements where possible and
proactively advertising Request for Proposal opportunity.