
COMMISSION AGENDA – Action Item No. 8d Page 2 of 7
Meeting Date: August 8, 2023
(Diversity in Contracting).
This project will help mitigate the impacts of WB aircraft gate outages during planned
construction, as it is necessary to meet current airport demand. Gate N14 improvements
include apron Portland cement concrete pavement (PCCP) panels, lighting, pre-conditioned air
(PCAir), 400 Hz power, Safedock, striping and two fuel hydrant pits and associated
infrastructure. Additionally, this project includes adding a starboard fuel hydrant pit (FHP) and
associated infrastructure improvements at Gate N16.
The project will improve safety, reduce emissions, and improve operational efficiencies at Gates
N14 and N16.
• Safety improvements include the reduction of fuel trucks operating within the
congested apron environment.
• Emissions reductions will be realized through upgrading ground power (400 Hz) and
PCAir units servicing WB aircraft at Gate N14 allowing airlines to shut down on-board
aircraft power units when parked at Gate N14.
• Operational efficiencies will be gained as Gates N14 and N16 will provide all airlines with
the ability to fuel either (or both) wing(s) of their WB aircraft, providing necessary gate
scheduling flexibility during planned construction projects.
Diversity in Contracting
The project team has been working with the Diversity in Contracting Department and will be
returning to the Commission for construction authorization along with an aspirational goal for
women and minority business enterprises (WMBE) participation in the construction contract.
The design services contract (P-00320884) includes a 15% WMBE participation requirement and
is currently trending below the requirement. However, Service Directive (SD) and associated
Modification for this project are estimated to provide 30% utilization, which will help the
overall Service Agreement utilization. The project management services contract (P-00320718)
includes a 16% WMBE participation requirement and is currently trending above the
requirement. The SD and associated Modifications for this project are estimated to continue
the positive trend with an estimated 23% utilization.
Long-lead Material Procurement
Certain construction materials and necessary project equipment may have lead times exceeding
standard contractor mobilization time frames. The project team has been analyzing the
construction bidding market to identify these critical material items including, but not limited to
utility covers, high mast light poles/luminaires, hydrant fuel pits, PCAir units, and Safedock
units. Early procurement of these items as owner furnished/contractor installed (OFCI) items
will help maintain the construction schedule and planned gate closures for Summer/Fall 2024.
As final design progresses the project team will confirm critical OFCI items and work with the
Central Procurement Office (CPO) to develop the most effective path forward.