Risks
7
Risk Impact Probability Mitigation Plan
VFDs to be replaced have been
approximated to 70, final count and
selection might change based on the
requirement and design criteria. The project
will aim to finish within budget even if the
count varies.
Risk will be accepted and monitored to avoid any
delay to the schedule. Increased overall project
contingency to 10% along with increasing design
development allowances to mitigate this risk. The
project team (PM, F&I) along with the design
team is responsible to finalize the selection and
count of VFDs.
16 weeks lead time to delivery for required
matrix industrial drives (VFDs) in 2023 which
was 54 weeks in 2022.
Owner Furnished Equipment approach was
initially planned during Acquisitions Planning
meeting in October 2022. Since the lead times for
VFDs are trending to reduce, Owner Furnished
Equipment was rescinded during Acquisitions
Planning meeting in May 2023.