Sustainable Airport Master Plan
Near-Term Projects Environmental Review
Update and Budget Request
Item No.10c supp
Meeting Date: June 27, 2023
Sustainable Airport Master Plan
Near-Term Projects
Additional passenger processing facilities and gates to accommodate
projected 56 Million Annual Passengers (MAP) at an optimal Level of
Service
Additional cargo facilities to accommodate projected cargo demand
Airfield infrastructure modifications to meet current Federal Aviation
Administration airport design standards
Improvements to enhance the efficiency of the overall taxiway layout
Additional fuel storage facilities to meet projected demand and the
Ports Sustainable Aviation Fuel initiative
2
Near-Term Projects
Undergoing Environmental Review
3
4
Environmental review analysis based on
constrained growth scenarios
Proposed Action
Constrained Scenario
No Action
Constrained Scenario
2024
Updated Schedule
5
NEPA EA Draft
Document
Agency and Public
Comment Period
(Q4 2024)
NEPA EA Agency &
Public Review
Complete
(Q1 2025)
NEPA EA Final Document
& Decision
(Early Q2 2025)
SEPA EIS Agency &
Public Review
Complete
(Mid Q3 2025)
SEPA EIS Final
Document &
Decision
(Q4 2025)
2025
Impact
Analysis
Draft
Sections
(June 2024)
2026
SEPA EIS Draft Document
Agency and Public
Comment Period
(Late Q2 2025)
= Key milestones
= Agency and Public Comment Period
Existing
Condition
Draft
Sections
(Aug. 2023)
Commission
considers/approves
project(s)
Budget Increase Justification
Schedule extension to update and complete analysis and
documentation
Factors requiring extended schedule
COVID-19 pandemic
Change in opening year of Sustainable Airport Master Plan (SAMP)
Near-Term Projects (NTP); from 2027, now 2032
Update of aviation demand forecasts
Update of technical analysis due to delay and new NTP opening year
6
Request
7
Authorization Total
Previous authorization (11/10/2015) $3,000,000
Previous authorization (2/25/2020)
Current request for authorization
$3,400,000
$2,350,000
Total authorizations, including this request $8,750,000