Project Risks and Opportunities
Risk /
Opportunity
Description Probability Impact Mitigation Plan
Risk
HVAC system improvements
constrained due to limited floor
clearance in SEA Garage
H H
Exploring two options through
30% design; included additional
project contingency for risk
Risk
GT Booth needs to remain in
operation during construction
H H
Developed phased approach to
construction
Risk
Existing plaza tile may be
damaged; product not available
for replacement
M M
Utilize a close match
replacement tile
Opportunity
Limited architectural standards
for facilities in SEA Garage
H L
Evaluate materials and finishes
and establish standard
9