Boiler Room Upgrades
Joe Cook
AV F&I Mechanical
Engineering Manager
Item No. 8c_supp
Meeting Date: May 23, 2023
Presenter: Tyler Salisbury - AV PMG
Project Manager: Christian Venturino -
AV PMG
Project Scope
Project replaces failing controls components of
Central Mechanical Plants heating system to
ensure continuous reliable supply of steam for
space heating and domestic hot water uses in
concourse and terminal areas.
Scope includes:
1. Modify Boiler #4 to allow dual-fuel (natural
gas and diesel) operation.
2. Install new Exhaust Gas Analyzer for Boiler #4.
3. Install new flow meters for Boilers #1-4.
4. Upgrade control panels.
5. Install boiler emergency shut down buttons.
2
Boiler #1
Boiler #2
Boiler #4
Boiler #3
Central Mechanical Plant (CMP)
Project Schedule
3
Milestone Date
Final Design Complete Q3 2024
Commission Authorization for Construction Q4 2024
Notice to Proceed Q1 2025
Substantial Completion Q1 2026
Project Budget
4
Cost Estimate Capital Expense Total
Original estimate $3,406,000 $0 $3,406,000
Current change $1,433,000 $0 $1,433,000
Revised estimate $4,839,000 $0 $4,839,000
Authorization Capital Expense Total
Previous authorizations $40,000 $0 $40,000
Current request for authorization $1,479,000 $0 $1,479,000
Total authorizations, including this request $1,519,000 $0 $1,519,000
Remaining amount to be authorized $3,320,000 $0 $3,320,000
Cone of Certainty
5
We
Are
Here
Action Requested
Increase the project budget for the Boiler Room Upgrades project in the amount of
$1,433,000
New total project budget of $4,839,000
Prepare design and construction bid documents for the Boiler Room Upgrades
project
Utilize Port of Seattle crews to support design and construction activities
Request to authorize $1,479,000
Estimated total project cost not to exceed $4,839,000
6
Questions?
7