
Template revised January 10, 2019.
COMMISSION
DATE: May 11, 2023
TO: Stephen P. Metruck, Executive Director
FROM: Keri Stephens, Director, Aviation Facilities and Capital Programs
Eileen Francisco, Director, Aviation Project Management
SUBJECT: Boiler Room Upgrades (CIP# 801230) – Design Authorization
Total estimated project cost:
ACTION REQUESTED
Request Commission authorization for the Executive Director to (1) prepare design and
construction bid documents for the Boiler Room Upgrades project; (2) utilize Port of Seattle
crews to support design and pre-construction activities. The amount of this request is
$1,479,000 for an estimated total project cost not to exceed $4,839,000.
EXECUTIVE SUMMARY
The central mechanical plant provides airport-wide steam and chilled water for cooling,
heating, and hot water purposes. This project will update components of the Boiler system to
allow for the continued operational ability to utilize both natural gas and diesel fuels, effectively
maintaining a layer of redundancy to the system in the event of a natural gas curtailment. This
project will install new and replace old steam supply and fuel flow meters, which will improve
energy use tracking and accuracy, leading to efficiency savings. This project will also upgrade
the control systems for Boilers #1 through #4 to include Siemens DDC integration. The
Deaerator and Condensate System Upgrade project, which was previously submitted to
Commission, also performs work on the Central Mechanical Plant’s heating system. However,
that project focuses on different components and will have an extended duration due to the
space constraint challenges present in the Central Mechanical Plant.
JUSTIFICATION
The central mechanical plant, which houses the boiler and chiller systems, provides the steam
and chilled water necessary for providing cooling, heating, and hot water to the main terminal,
concourses, and North and South satellites. It is an essential element of the airport, and it is