Project Scope & Coordination
Project Scope:
Pile Wrap at (92) steel piles at the south apron
Cathodic Protection Anode Replacement at
(498) steel piles at BHM and Pier 66.
Coordination:
Permitted in-water work window
Facility operations: cruise season, rec boating
events schedule, etc.
Simultaneous projects: Pier 66 Fender
Rehabilitation & Shore Power projects
Project Info
5
Cost Breakdown This Request Total Project
C800539 C800517 C800539 C800517
Current Authorization $0 $0 $230,000 $130,000
Design $395,000 $420,000 $625,000 $550,000
Construction $0 $0 $2,125,000 $1,200,000
Total per project $395,000 $420,000 $2,750,000 $1,750,000
Total both projects $815,000 $4,500,000
Project Timeline
6
Activity Date
Design Authorization WPM DOA Workflow Q1 2023
Design Start (Docks Diving IDIQ pending execution) Q2 2023
Construction Authorization WPM DOA Workflow Q1 2024
Construction Start, (2) work windows
(Fish window: 8/1/24 1/15/2025)
Q4 2024
In-use date Q1 2026