Template revised January 10, 2019.
COMMISSION
AGENDA MEMORANDUM
Item No.
8e
ACTION ITEM
Date of Meeting
March 28, 2023
DATE: March 21, 2023
TO: Stephen P. Metruck, Executive Director
FROM: Darrell Dare, Sr. Manager Recreational Boating
Marie Ellingson, Sr. Manager Cruise Ops and Business Development
Julie Yun, Capital Project Manager
SUBJECT: Bell Harbor Marina Pile Wrap and Cathodic Protection (CIP #C800539)
Pier 66 Break Water Cathodic Protection (CIP #C800517)
ACTION REQUESTED
Request Commission authorization for the Executive Director to authorize $815,000 ($395,000
for C800539 / $420,000 for C800517) to complete design and permitting for the Corrosion
Protection projects at Bell Harbor Marina and Pier 66, including overall cathodic protection
replacement and south apron pile wrap.
EXECUTIVE SUMMARY
Built in the mid-1990s, Pier 66 and Bell Harbor Marina (BHM) support several functions including
public-use recreational marina and berthing for cruise ships and other vessels. The steel piles
supporting the pier structure at Pier 66 and BHM were coated at the time of installation to
withstand marine water conditions. The recent condition assessment from 2021 monitoring the
condition of the steel piling has revealed that the corrosion protection system has reached the
end of its life. Varying degrees of coating oxidation and anode depletion are evident. This memo
requests Commission approval for $815,000 for design, permitting, and project management for
a new corrosion protection system at Bell Harbor Marina and Pier 66. This system includes pile-
wrap for the inter-tidal zone and cathodic protection for the submerged portions of the steel
piling for a target design life of 30-50 years. This project aims to preserve the existing asset and
is reflected in the 2023 Plan of Finance. The total project cost is estimated at $4,500,000
($2,750,000 for C800539 / $1,750,000 for C800517). Following design, staff will return to
Commission to seek authorization for construction.
JUSTIFICATION
This project supports the following Century Agenda and Maritime Division priorities:
(1) Advance this region as a leading tourism destination and business gateway.
Amount of this request:
$ 815,000 ($395,000 - C800539 / $420,000 - C800517)
Total estimated project cost:
$ 4,500,000 ($2,750,000 - C800539 / $1,750,000 - C800517)
COMMISSION AGENDA Action Item No. 8e Page 2 of 5
Meeting Date: March 28, 2023
Template revised June 27, 2019 (Diversity in Contracting).
(2) Asset Management Develop, maintain, and operate Maritime facilities to ensure long-
term viability and efficiency, to meet our customer’s needs.
Corrosion Protection systems include coating systems, pile wrap, and cathodic protection and
are a critical element of steel pile maintenance of Port waterfront facilities. Past condition
assessments monitoring the condition of the steel piling have revealed that various elements of
the corrosion protection system at Pier 66 and Bell Harbor Marina have reached the end of their
design life. Varying degrees of coating oxidation and anode depletion are evident. This project
proposes to install pile wrap and replace the existing cathodic protection system on steel piles
supporting Bell Harbor Marina and Pier 66, thereby preventing continued corrosion and
extending the assets’ useful life.
Diversity in Contracting
Project design will leverage a Docks and Diving IDIQ Contract (currently in procurement) that
will have an overall women and minority-owned business enterprise (WMBE) goal of 15%.
DETAILS
Scope of Work
This project will design and install a new corrosion protection system at Bell Harbor Marina and
Pier 66. At Bell Harbor Marina, a pile-wrap system for the inter-tidal splash zone will be installed
(similar in scope to the WP#104616 and 104663 Pier 66 and Pier 69 Corrosion Control projects in
2013-2014) at (92) 24” steel piling. At both Pier 66 and Bell Harbor Marina, the cathodic
protection system will be replaced to protect the submerged portions of (498) steel piling of
varying sizes (18” to 24diameter) below the inter-tidal splash zone. At Pier 66, the currently
depleted cathodic protection system will be replaced to protect the submerged portions of steel
piling below the inter-tidal splash zone.
Schedule
This project is expected to occur over (2) in-water work windows based on coordination with the
permitted fish window under the Port’s 10-year Pile Programmatic Permit (pending renewal Q2
2023), seasonal Cruise and Rec Boating activity, and simultaneous Port capital projects at BHM
and Pier 66 (Pier 66 Shore Power, Pier 66 Fender System Rehabilitation). Pile wrap and
replacement anode materials are not anticipated to have long procurement lead times.
Activity
Commission design authorization
2023 Q1
Design start
2023 Q2
Commission construction authorization
2024 Q1
Construction start
2024 Q4
In-use date
2026 Q1
COMMISSION AGENDA Action Item No. 8e Page 3 of 5
Meeting Date: March 28, 2023
Template revised June 27, 2019 (Diversity in Contracting).
Cost Breakdown
This Request
Total Project
C800539
C800517
C800539
C800517
Design
$395,000
$420,000
$625,000
$550,000
Construction
$0
$0
$2,125,000
$1,200,000
Totalper project
$395,000
$420,000
$2,750,000
$1,750,000
Total both projects
$815,000
$4,500,000
ALTERNATIVES AND IMPLICATIONS CONSIDERED
Alternative 1Defer the design and permitting scope of work identified for this project.
Cost Implications: Reduces needs in the Capital Plan by $815,000.
Pros:
(1) Retains Port capital and staff resources for other priority projects and financial
initiatives.
(2) Defers temporary construction impacts.
Cons:
(1) Continued corrosion and deterioration of the steel piles supporting Bell Harbor Marina
and Pier 66.
(2) Increased risk of failure and higher cost of repair/replacement as compared to
preemptive corrosion control.
This is not the recommended alternative.
Alternative 2 Proceed with design and permitting of corrosion control project scope as
proposed.
Cost Implications: requires allocation of $815,000 in the Capital Plan.
Pros:
(1) Preservation of critical assets to support long-term use and revenue generation at Bell
Harbor Marina and Pier 66.
(2) Good durability to initial cost ratio (30-50- year design life).
(3) Minimize risk of failure and subsequent operational disruption through preemptive
corrosion control measures.
Cons:
(1) Temporary coordination and impact to Bell Harbor Marina and Pier 66 during
construction.
This is the recommended alternative.
COMMISSION AGENDA Action Item No. 8e Page 4 of 5
Meeting Date: March 28, 2023
Template revised June 27, 2019 (Diversity in Contracting).
FINANCIAL IMPLICATIONS
Cost
Estimate
/Authoriza
tion Summary
Capital ($1000)
Total ($1000)
COST ESTIMATE C800539 C800517 Both
projects
C800539 C800517 Both
projects
Original estimate
$4,360
$1,150
$5,510
$4,360
$1,150
$5,510
Current change
($1,610)
$600
$1,010
($1,610)
$600
$1,010
Revised estimate
$2,750
$1,750
$4,500
$2,750
$1,750
$4,500
AUTHORIZATION
Previous
authorizations
$230
$130
$360
$230
$130
$360
Current request
for authorization
$395
$420
$815
$395
$420
$815
Total
authorizations,
including this
request
$625
$550
$1,175
$625
$550
$1,175
Remaining amount
to be authorized
$2,125
$1,200
$3,325
$2,125
$1,200
$3,325
Annual Budget Status and Source of Funds
Both projects are included in the approved 2023 Capital Plan under C800539 BHM Pile Wrap and
Cathodic Protection ($4.3M) and C800517 P66 Wave Break Cathodic Protection ($1.M) with a
total project cost of $5.31M.
Both projects are funded by the General Fund.
Financial Analysis and Summary
Project cost for analysis
$5,309,000
Business Unit (BU)
Recreational Boating/Cruise and other vessel Operations
Effect on business performance
(NOI after depreciation)
No incremental operating revenue is associated with
this project.
Estimated useful life of infrastructure is between 30-
50 years, resulting in a depreciation expense of
$106k-$177k annually. NOI after depreciation will
reduce by that respective amount.
IRR/NPV (if relevant)
N/A
CPE Impact
N/A
COMMISSION AGENDA Action Item No. 8e Page 5 of 5
Meeting Date: March 28, 2023
Template revised June 27, 2019 (Diversity in Contracting).
Future Revenues and Expenses (Total cost of ownership)
Annual depreciation expenses will increase after the capital project is completed; however, as a
preemptive corrosion control project, this will mitigate increased risk of failure that would have
a significant impact on revenue and also decrease expenses for higher cost of
repair/replacement.
ADDITIONAL BACKGROUND
This project allows the Port to continue to provide safe and versatile piers. As such, it is funded
by the general fund (comprised of revenues generated from the marina, cruise passenger feeds,
and dockage fees) allocated for maintaining Port assets, avoiding costly repairs, and safeguarding
the ability to offer uninterrupted premium facilities.
ATTACHMENTS TO THIS REQUEST
(1) Presentation slides
PREVIOUS COMMISSION ACTIONS OR BRIEFINGS
None