
Template revised January 10, 2019.
COMMISSION
DATE: March 9, 2023
TO: Stephen P. Metruck, Executive Director
FROM: Kelly Purnell, Capital Project Manager
Jessica Carlson, Senior Real Estate Manager
Melinda Miller, Director, Real Estate Asset Management
SUBJECT: Fishermen’s Terminal Bank Building (C-12) Demolition
Total estimated project cost:
ACTION REQUESTED
Request Commission authorization for the Executive Director to advertise and execute a major
works construction contract to demolish the Fishermen’s Terminal Bank Building (C-12). This
request is for $440,000 of a total project cost of $496,000.
EXECUTIVE SUMMARY
The project will demolish the existing Fishermen’s Terminal Bank Building (Building C-12) which
is vacant and is unleasable due to the poor condition of the structure. The work will include
abatement of regulated materials, small amounts of material salvage such as the bank vault door,
demolition of the structure to existing slab, and removal of existing landscaping including curb
and gutter on the site. Capping of the utilities (water, sewer, electric) will be required. A handhole
will be installed for the electricity to provide for access for temporary power connection for a
construction job shack in future. Crushed rock will be placed in existing landscape area. No paving
or addition of any new impervious surface will be included in the work.
JUSTIFICATION
The Fishermen’s Terminal Bank Building has been slated for demolition since 2017 and was
vacant for several years before that. The building is currently in disrepair. Much of the interior
has been stripped out and has undergone partial regulated materials abatement of the interior.
Additionally, the building has suffered from repeated break-ins.
Originally, the property was to be redeveloped as part of the Gateway Building and the overall
Fishermen’s Terminal Long-term Strategic Plan. While that is still the anticipated future use of