
COMMISSION AGENDA – Action Item No. 10c Page 2 of 8
Meeting Date: March 28, 2023
Template revised June 27, 2019 (Diversity in Contracting).
As the design has progressed several items have been added to the Program work to resolve pre-
existing building and fire code compliance issues. The impacts of these corrective actions on
follow on projects/programs in the Main Terminal are also directly influencing the design
approaches being used to address these items.
As a result, establishing the final Phase B construction cost and the Final Guaranteed Maximum
Price (FGMP) for the overall Program have been delayed. Staff intends to return to the
Commission for authorization of these remaining items on 06/27. Currently, the estimated cost
for these, including associated Port and Alaska soft costs, is approximately $50 million. The
current estimated cost for the overall Program is $550 million.
JUSTIFICATION
The ticketing area used by Alaska at the north end of the Main Terminal regularly experiences
serious overcrowding during peak departure periods throughout the day and is in critical need of
code upgrades as well as an update to the architectural finishes.
Although previous work was done by Alaska to alleviate passenger queuing and processing
gridlock, more than 10 years later the ticketing area is again in need of modernization to address
existing and projected passenger volume increases, keep pace with technology advances and
improve the overall passenger experience.
The Port anticipates completing similar building system and architectural improvements for the
remainder of the terminal to the south under the upcoming Main Terminal Improvements
Program (MTIP), which is currently in the Program Definition Document phase.
With its current staggered screening lane layout, Checkpoint #5 has long been unable to
accommodate increased passenger volumes, regularly resulting in a processing bottleneck during
peak travel periods that creates further delays for departing passengers. Phase B work will
reconstruct Checkpoint #5 to have 6 side-by-side lanes and provide a greatly enlarged recompose
area for passengers, which is a significant improvement over the current configuration. Further,
the Checkpoint #5 reconfiguration is being phased and coordinated with work planned at other
screening checkpoints to minimize the number of search lanes out of service at any given time.
Determining the method and extent of correcting the previously described fire and building code-
related compliance issues has become a precondition for the Airport Building Department to
issue building permits and later, certificates of occupancy for the Program. These items include:
1. Providing 1-hr fire rating compliance at the wall separating the Baggage Claim from the
Bagwell within the Program scope of work.
2. Providing 2-hr fire rating compliance at vertical utility shafts within the Program scope of
work.
3. The addition of fire sprinklers in Skybridges 2 through 6 to allow occupancy of the newly
constructed tenant and operational spaces on the Bridge/Promenade level.