Concourse HVAC Infrastructure Renewal and
Replacement Program (CHIRRP)
Seattle-Tacoma
International Airport
Item No. 8k_supp
Meeting Date: March 14, 2023
Aging Infrastructure Impacting Critical Programs
2
Airport Dining and Retail Restroom Renovations
Passenger Amenities
Maintaining Our Assets: Investing In Our
Current Facility
3
Concourse B
Last Renovated 1990
(31 years)
Concourse C
Last Renovated 1990
(31 years)
Concourse D
Last Renovated 1990
(31 years)
CHIRRP PROJECT PLANNING
4
Phased
Construction
Design /
GCCM
Project
Definition
Document
Planning
We are here
5
CHIRRP
Concourse HVAC
Infrastructure Renewal &
Replacement Program
Renew and Replace Aging Air
Handler and HVAC Infrastructure
Refurbishment/Replacement of
associated utilities
Address relevant code compliance
issues
Ceiling & Lighting renewal and
replacement
Ceiling mounted
equipment/signage renewal and
replacement
CHIRRP PROJECT SCOPE SUMMARY
CHIRRP Alternatives Comparison
6
Scope Items Included in Program
Alt 3
(Recommended)
Alt 2
(Highest Cost)
Replace, Refurbish, or Add Supplemental Air Handlers X X
Emergency Power System Upgrades X X
Upsize and Replace Hydronic Heating Water Distribution and Chilled Water Distribution X X
Concourse Ceiling Replacement (No Holdrooms or ADR) X X
Fire Sprinkler, Fire Risers, Exit Signs X X
Security Camera Updates X X
Ceiling Mounted Signage X X
Raise Roof Structure to Raise Concourse Ceilings X
Ceiling Replacement in Circulation, Holdroom, and ADR/Tenant Spaces X
Complete Air Distribution System Re-design X
ENERGY
REDUCTION
Opportunity for energy
reduction with HVAC
refresh, efficient LED
lighting, and updated
lighting controls.
Compliance Evaluation with
upcoming State of
Washington Clean Buildings
Performance Standards
Contribute to Century
Agenda goals around energy
efficiency, reducing SEAs
footprint and lowering
costs.
8
Project Schedule
*Schedule to be further refined within the Project Definition Document (PDD)
**Project will return to commission for remaining design authorization and
further updates near completion of the PDD in Q3/2024.
Commission PDD Authorization 2023 Quarter 1
Commission Design Authorization (through 30%) 2023 Quarter 1
PDD Start 2024 Quarter 1
**Commission Remaining Design Authorization 2024 Quarter 3
Design Start
2025 Quarter 1
Commission Construction Authorization 2027 Quarter 2
Construction Start 2027 Quarter 3
In-use date 2031 Quarter 3
Questions?