Risks
6
Risk Description Probability Impact Mitigation Plan
Material shortages Long-lead times
associated with
stainless steel
piping
H H
Identify long lead time materials
and work with designer and
construction team to order
materials as quickly as possible.
Minimal space
available for pipe
routing
Areas where pipe is
being installed is
congested with
various other
infrastructure
H H
Identify issues early and work
with designer to find alternative
pathing, as needed
Restroom and
concession
temporary closures
Replacement of
pipes will require
temporary closures
to restrooms and
concessions
H M
Work with AV Public Relations,
ORAT, AV F&I Signage, AV
Operations, and ADR early to
provide signage and do work in
hours that least impact the
public