Funding Request Timeline
$50K in 2020 Q3 for design & permitting via EX-2 delegation schedule.
$200K in 2021 Q2 for construction via EX-2 delegation schedule.
2021 Q3 & Q4 dedicated to finalizing design and SCL service letter & reviewing electrical equipment
submittals prior to procurement in December.
Experienced 5-month delay in receiving critical electrical components, losing favorable weather window for
construction. (Anticipated April 2022 – Received September 2022)
A slight change in angle for the rigid conduit sweep for the main power distribution resulted in
unanticipated excavation through SDOT roadway panels.
$50K in 2023 Q1 for construction via EX-2 delegation schedule.
Intended as a stop-gap measure to avoid work shutdown while preparing Commission documents.
$150K in 2023 Q1 via Commission Approval for a total project cost of NTE $450K.
Current funding request to encompass all remaining work tasks for project completion in Q2 2023.
5