
COMMISSION AGENDA – Action Item No. 8g Page 2 of 4
Meeting Date: March 14, 2023
Template revised June 27, 2019 (Diversity in Contracting).
project will allow for future installation of EV charging stations, and provide additional capacity
for lighting enhancements, security systems, or other specific items needing a dedicated power
connection. Future installation of EV charging stations at this location will not only reduce carbon
emissions and contribute to achieving Port Century Agenda Goal 4 but is critical to keep pace
with the procurement and arrival of electric Maintenance Fleet vehicles. A separate capital
project is currently in the planning phase to design and install a maximum quantity of EV charging
stations allowable in the MM South Yard given the additional electrical service capacity provided
by this Commission request.
Diversity in Contracting
The Diversity in Contracting Department has not been contacted regarding this project and no
WMBE aspirational goals or inclusion plans were established, as it is intended to be completed
using Port design staff and construction labor with no external workforce utilization. An
Acquisition Planning meeting was conducted in November 2021 prior to requesting construction
funding.
DETAILS
This project will increase electrical service in the MM South Yard from 100A to 600A capacity
through installation of upgraded SCL pole mounted transformers, construction of new electrical
switchgear in the MM South Yard, cutover of power connection by SCL, and demolition of existing
switchgear followed by MM yard and SDOT roadway panel restoration.
Scope of Work
Work completed to date includes installation of SCL pole mounted transformers per the SCL
service letter agreement, installation of the below grade main power feed from SCL transformers
to the MM South Yard equipment pad, and 90% construction completion of the new electrical
switchgear. Remaining tasks include final buildout of the electrical switchgear and intercepting
below grade conduit connections, installation of meters and final power cutover by SCL,
demolition of existing switchgear and restoration of MM South Yard pavement, and restoration
of two SDOT roadway panels at the base of the SCL utility pole on S. Hinds St. that were excavated
during trenching for the main power feed connection.
Schedule
Activity
Project Mgmt. / Env. Permitting