Communication Enhancement
Tyler Salisbury – AV-PMG
C801161
March 14, 2023
Item No. 8c_supp
Meeting Date: March 14, 2023
Project Overview
2
• Demand for High
speed and capacity
data connections are
growing.
Background
3
Project Scope
• Add connections to 30 comm rooms (≥85% capacity)
• Use existing cable tray infrastructure
• New fiber runs between the Main Distribution Rooms (MDR)
and comm equipment rooms
4
Budget and Authorizations
Budget Project Budget
Design $3,160,000
Construction $7,840,000
Total $11,000,000
5
Authorizations Project Budget
Previous authorization $3,160,000
This request $7,840,000
Total authorized amount (Including this request) $11,000,000
Remaining to be authorized $0
Schedule
• Commission Authorization for Construction: 1Q 2023
• Bid Advertisement 2Q 2023
• Issue Notice to Proceed: 1Q 2024
• Substantial Complete: 2Q 2025
6
Cost and Schedule Project Estimating Certainty
DIVISION APPROVED
AUTHORIZED
IN PROGRESS
COMPLETE
Managing Director
approved
Commission authorized design
Commission Authorization
3
4
5
6
Staff level authorization for cost
and schedule estimates
Refine cost and schedule estimates up to
100%
Construction
7
Degree of Uncertainty
We are here
Communication
Enhancement
Risks and Operational Impacts
RISK DESCRITPITON PROBABILITY IMPACT MITIGATION PLAN
Supply Lead time for Fiber
Optic Cabling
Industry wide supply chain issues have led
to volatility in materials delivery time. Fiber
optic cabling has had the lead time vary
during the design timeline.
Medium High The design team has been working
to confirm the fiber quantity
needed and verify expected lead
times for our region.
CIBS tray access Most of the trays are run in the ceiling
space of the bag well and can be difficult to
access.
High Medium Installation operations will need to
be planned with baggage
operations in mind. Tug detours,
temporary shut down requests for
bag line, and coordinating with
ongoing projects.
Multiple project
coordination
Project team will need to work closely with
other projects and evaluate changing
environments. Baggage optimization, Main
Terminal projects, and Tenant projects
Medium Medium Critical reviewers have been
included on the design reviews.
Additional site walks and
discussions will be needed to
coordinate access and minimize
schedule impacts.