COMMISSION AGENDA – Action Item No. 8i Page 3 of 8
Meeting Date: February 14, 2023
Template revised June 27, 2019 (Diversity in Contracting).
DETAILS
A detailed code analysis of Concourse B identified significant code deficiencies initiating restroom
improvements not previously included in the project and the need for an interior corridor to be
constructed at the ramp of Concourse B. An Enabling work package is required to facilitate initial
infrastructure relocations and construction activities necessary to bring Concourse B Ramp
operational space to full code compliance. The existing Air Handling Units (AHUs)and Heating,
Ventilation, and Air Conditioning (HVAC) system have been a known deficiency for the Airport
and scheduled to be updated under a future airport-wide project. The increase in leasable square
footage and building occupancy necessary on B Concourse for Airline Realignment requires the
project accelerate the future AHU and HVAC scope of work to meet minimum code requirements.
Additionally, scanning and subsequent building information modeling (BIM) efforts facilitated
through the GCCM Pre-Construction contract, are identifying the location and extents of
unknown and unforeseen existing utilities. In support of the schedule milestone deliverables, the
Design Team has continued to progress all five work packages to approximately 15% design
development.
The project-specific design contract amendment that would increase the contract value by
$5,200,000 would bring the contract total value to $10,200,000. In accordance with RCW
53.19.060, this memorandum constitutes notification to the Commission that the amended
amount of the design contract exceeds 50 percent of the original not-to-exceed contract value.
Additional GCCM Pre-construction services are required to identify existing conditions and
provide as-built documentation. The activities represented by the contract changes are required
to support the remaining design development and have been reevaluated, informed through site
investigation and preliminary design coordination. Documentation of existing conditions for
Concourse B to support this project is either deficient or missing. This has driven a need for the
GCCM to provide additional laser scanning, 3D space modeling, and site investigation activities
not previously anticipated. To maintain progress, the GCCM pre-construction contract
(established at $900,000) required a change order in the amount of $281,105.87. This was
executed from project contingency funds in January. The GCCM change order included in this
action will fully fund pre-construction support activities through the balance of the schedule.
These efforts support design progression, the current GCCM Pre-construction Bid Package
Schedule and ultimately limit delays in relocating airlines.
The project will be returning to the Commission in Q2 2023 after design has reached a 30% level
of completion to establish a more definitive project budget and schedule. The current project
budget range relies on a Class 5 Estimate that captures the conceptual scope and projected
project costs prior to 30% design development.
Current project risks that represent the majority of potential cost increases can be attributed to:
(1) Industrywide inflation and cost escalation since the project budget establishment in 2021.