North Employee Parking Lot Improvements
Construction Authorization
for Phase 2
Item No.
8j_supp
Date of Meeting January 24, 2023
Project Location
North Employee Parking Lot
(NEPL)
• Parking for airport employees
• 4,122 parking stalls
• 11,170 parking permits
(maximum 12,000)
2
24
th
Ave S
S 146
th
St
N
Project Purpose
Purpose:
Extend the life of the North Employee Parking Lot and improve customer
service and operational support.
Phasing:
• Phase 1: Bus Shelters and limited site features
• Phase 2: Failing infrastructure (retaining wall, electrical feeders) and way
finding signage
• Phase 3: Pavement and underlying failing infrastructure (watermain, storm
channel drains) and potential EV parking expansion
3
Replacement of:
• Failing rockery retaining wall
• Failing electrical feeders
• Aged wayfinding signage
Project Scope (Phase 2)
4
Previous Budget $7,246,000
Budget Change $1,632,000
Revised Budget $8,878,000
Current increase due to:
• Retaining wall type (geotechnical
requirement)
Key Schedule Milestones:
• Construction Start: Q2 2023
• In-Use Date: Q4 2023
Project Budget and Schedule (Phase 2)
5
Cost Certainty
6
NEPL Phase 2