Project Update
Currently $8,620,000 is Approved for 11 Pieces of SRE
– Ramp team SRE equipment has been ordered
– The (8) ordered units will arrive early 2023, first piece of snow equipment arrived in November 2022!
In process of procurement for remaining SRE
– Currently have approval for (2) Blowers and (1) Deicer truck but would like to increase scope due AIP fund availability.
3
4
• Snow Broom SRE would be replaced 1 year ahead of previous plan
• Airport ended 2022 with uncommitted FAA AIP entitlement grants; acceleration of
the SRE acquisitions an eligible use of those funds
Request to add (4) Snow Brooms to Authorization
Example of Snow Broom SRE to the right.
This is type of SRE would be procured if approved. Current
equipment is model year 2008 and should be replaced due to age
and productivity. If approved the SRE being replaced would be over
16 years old once replaced.
AIP Fund Request for Snow Equipment
• AIP funds are available for (2) blowers, (1) deicer truck, plus (4) broom systems
• AIP funds 75% of SRE acquisition cost
• Net reductions of Port revenue bond funding by ~$1M
5
Above are examples of remaining types of SRE currently authorized to procure.
Airfield deicer truck on the left and a snow blower is on the right.
Proposed Funding Changes
6
• Currently approved for $8.6M against CIP801227; proposed funding $11.6M
• AIP Entitlement could cover ~$4M worth of equipment cost if approved to add (4)
Broom Systems to procurement
• Reduces Airport contributed funding from CIP801227 from $8.62M to ~$7.62M
Current SRE Replacement Plan
Proposed SRE Replacement Plan
Year Replacing Airport Cost AIP*
2022-2024 11 $8.6M -
2025 4 $3.2M -
2027 8 $8M -
2028 1 $0.5M -
*Original plan of finance did not include AIP grants; 8 of 11 SRE not AIP
eligible
Year Replacing Airport Cost AIP Total
2022-2024 15 $7.6M $4M $11.6M
2025 - - - -
2027 8 $8M - $8M
2028 1 $0.5M - $0.5M
Summary
• Request authorization to add (4) pieces of snow removal equipment to current
procurement
• Total request would be updated from $8.6M to $11.6M with ~$4M coming from AIP
entitlement funds
7