COMMISSION AGENDA – Action Item No. 8b Page 6 of 7
Meeting Date: January 24, 2023
Template revised June 27, 2019 (Diversity in Contracting).
Annual Budget Status and Source of Funds
This project, C800612, was included in the 2023-2027 capital budget and plan of finance with a
budget of $954,134,000. This project has prior Majority In Interest (MII) airlines approval for
Phase 1 and 2. The Phase 3 MII ballot is anticipated in 2024. The funding sources would be airport
development fund and revenue bonds.
Financial Analysis and Summary
Project cost for analysis
Effect on business performance
(NOI after depreciation)
NOI after depreciation will increase due to inclusion of
capital (and operating) costs in airline rate base
$0.26 in 2020, $1.03 in 2024 and $2.75 in 2028
ATTACHMENTS TO THIS REQUEST
None
PREVIOUS COMMISSION ACTIONS OR BRIEFINGS
• July 26, 2022 – Request Commission authorization for the Executive Director to: (1) execute
an agreement with the Transportation Security Administrative (TSA) to provide clear access to
screening equipment for Phase 2, (2) authorize $34,215,000 for Phase 3 to complete pre-
construction services, (3) utilize, advertise, and execute a General Contractor/Construction
Manager (GC/CM) for Phase 3, (4) advertise and execute a project specific Construction
Management (CM) and Airline Technical Representative (ATR) contract for Phase 3, (5) amend
Service Agreement (SA) P-00317641 to add $18,340,000 for a total contract value of
$49,500,000 to complete design services and provide construction support for Phase 3, and
(6) utilize Port crews for Phase 3 activities, for Baggage Optimization Project at Seattle-Tacoma
International Airport. The total amount of this request is $34,215,000.
• April 19, 2022 – Baggage Optimization Program Update – Quarter 2, 2022
• January 28, 2020 – Commission Authorization to: (1) execute a construction contract with the
low responsive and responsible bidder for the Baggage Optimization Phase 2 Project at
Seattle-Tacoma International Airport, notwithstanding the low bid exceeding the estimate at
time of bid by more than 10 percent, and (2) authorize an additional $190,737,800 for Phase
2 construction and Phase 3 design for a total program authorization of $540,050,000.
• April 23, 2019 – Commission Authorization to: (1) advertise, award, and execute a construction
contract for the Baggage Optimization Phase 2 project at Seattle-Tacoma International
Airport; (2) employ a project labor agreement (PLA); and (3) utilize Port crews and small works
contracts to perform construction work.
• February 26, 2019 – Baggage Optimization Quarter 4 Project Briefing
• October 23, 2018 – Baggage Optimization Quarter 3 Project Briefing