Delegation of Authority
King County has a biennial budget that is approved by the 9-member council. Part of the budget process
includes approval of the CIP, which details out the major capital projects for the year and the related
spend. The City of Seattle has a similar process, whereby its budget and CIP approval is the key
authorization mechanism from the governing body. The Port also has an annual budget and CIP that is
approved by the governing body. However, the Port has an additional control, by which, prior to any
contract over $300,000 being executed, approval of the Commission is needed. Memos and PowerPoint
Presentations are prepared for this, and the average Memo is revised 30 times with various touchpoints
within the Port and approximately 15 hours is spent on each iteration of the Memos
1
.
In September of 2018, Sound Transit passed resolution R2018-40 to ensure that the Board’s time was
optimized on key issues facing the agency. This resolution delegated up to $50 million to the Standing
Board Committees for contracts, agreements, and real property agreements. It also delegated, up to $5
million to the CEO for the approval of competitively procured construction contracts and architectural
and engineering services contracts, and up to $2 million to the CEO for the approval of competitively
procured materials, technology, and other services contracts.
Internal Audit also conducted interviews with several business leaders at the Port. During these
interviews, we asked for feedback on the time and resources used to prepare materials for Commission
authorization. We commonly heard that an inordinate amount of time is spent gathering information,
revising material, and preparing for Commission presentations.
Recommendations:
Based on our discussions with management, review of data, and benchmarking with other organizations,
we recommend that management work with the Commission to identify if the current process and
thresholds can be modified to maintain or increase transparency and governance, while alleviating part
of the burden on staff. Sound Transit held an open public meeting in 2018, as part of a board workshop,
prior to making substantial changes to their delegation of authority. Where possible, the Port should also
consider leveraging standing committees to achieve efficiencies and increase transparency.
Internal Audit also advocates applying a risk-based approach, to determine items that require full
commission attention. Risk factors not only include financial exposure that the Commission is willing to
delegate to management, but should also include non-financial factors, such as social, environmental,
reputational or regulatory elements.
If limits are raised, we also recommend frequent (monthly) and robust reporting to the Commission and
the public. This approach would allow for a “passive approval” while preserving Commission oversight
and transparency. Raising the limit could also result in management spending more effort on “value
added” activity and simultaneously allowing the Commission more time to maintain their strategic focus.
Management Response/Action Plan:
We concur that this audit found that the Port’s Delegation of Authority controls were operating correctly
and that no concerns were found. An opportunity for greater efficiency was noted and we agree that
efficiencies could be gained with a risk and lean based approach to raise the overall, and/or selected
aspects, of the delegation limit to the Executive Director (ED). The impact of delegations spans many
employees across operations, capital, and corporate functions, and ranges through staff levels, to
management and executives, and all the way to the Commission. Increasing delegation limits may speed
staff work, and ultimately may free up Commission’s time for other important and strategic work.
1
September 27, 2017 Aviation Program Management Group Study of 26 Commission Memos. Unaudited directional Information.