Project Risks
RISK DESCRIPTION PROBABILITY IMPACT MITIGATION PLAN
Project Coordination Project Construction schedule
tied to the Baggage Optimization
and C1 expansion projects
finishing utility and build-out
work at the Central Terminal
Ramp by Q1 2023.
L M
Critical reviewers have been identified from
surrounding projects to reduce impacts and
overlap. Coordination meetings are ongoing.
Complex Construction Multi-phasing plan to maintain
egress and operational
requirements. Contractors
concerned with space and time
constraints.
M M
Gate B1 will be out of service to relieve some of the
space concerns.
Work Affecting Tenant
Operations
Requires move of tenant
refrigeration units affecting
food/perishable storage.
M L
Working with ADR on timing and duration of
outages. Project will provide new condenser units
and pressure test the new assembly prior to cut
over. Alternative storage will be provided.