Pier 66 Shore Power Project Construction Funding
Item No.: 10a_Supp
Meeting Date: January 10, 2023
• Commissioned in 1999
• Single berth facility and home port to
Norwegian and Oceania vessels
• Upgraded to accommodate newest NCL
vessels in 2018
• Recent P66 Interior Modernization
further enhanced areas jointly used by
Cruise and the International Conf. Center
• Contributes to significant jobs and
economic benefits to the region: 5,500
jobs and nearly $900M in total business
revenue each typical cruise season
Pier 66 Bell Street Cruise Terminal
2
Maritime Climate and Air Action Plan:
• Implement the Seattle Waterfront Clean
Energy Strategy
• Install cruise shore power at Pier 66 by
2024, 6 years ahead of the Northwest Ports
Clean Air Strategy goal
• Work with cruise lines to make 100% of
homeport calls shore power-capable
and plug in by 2030, if not before
• Incorporate sustainability best practices
into leases and agreements
Shore Power is a Key Environmental Strategy
3
• 93 percent of electricity in Seattle comes from low carbon,
low-cost sources, like hydroelectricity
• Ships that use Seattle’s clean electricity instead of fossil fuels
at berth reduce CO
2
and air pollutants
– In 2019 shore power use reduced about 2,900 metric tonnes of CO
2
– In 2021 shore power use reduced about 1,700 metric tonnes of CO
2
– In 2022 shore power use reduced about 2,200 metric tonnes of CO
2
• Cruise lines are demonstrating commitment to use shore
power at Terminal 91 and connection rates by equipped calls
increase year-over-year:
• At Pier 66, many ships are already shore power-equipped and
expected to connect once a connection is available
Shore Power Environmental Benefits and Successes
4
53%
62%
89%
97%
0%
20%
40%
60%
80%
100%
2017 2018 2019 2020 2021
5
Pier 66 Shore Power Project Components
Four key segments
• Segments 1 & 2: Landside infrastructure
at Terminal 46. Cost sharing with Seattle
City Light on Segment 1.
• Segment 3: Approximately 1-mile
submersible cable in Elliott Bay
• Segment 4: Shore power equipment and
infrastructure on Pier 66. Two shore
power connection points with cable
management system to offer connection
flexibility
Project Status
• Pre-Procurements executed for Submarine Cable and Electrical Equipment
• 90% design completed to accommodate alternate feeder source
• Permit review underway, approval expected Q1 2023
• Continuing collaboration with our partners on design development:
6
ï‚§ Northwest Seaport Alliance ï‚§ Seattle City Light
ï‚§ Washington State Ferries ï‚§ Seattle Dept. of Construction and Inspection
ï‚§ Tribal Governments ï‚§ Department of Natural Resources
ï‚§ Army Corps of Engineers ï‚§ Washington State Fish and Wildlife
ï‚§ National Marine Fisheries ï‚§ US Coast Guard
Authorization Request
• Advertise and award Major Works Contract to complete construction
work, extend design contracts to cover construction support.
• Execute a Memorandum of Agreement with Seattle City Light and
associated agreements (incl. property and DNR easement) to facilitate
this work
• Execute Tribal mitigation agreements
Total amount of this request: $29,145,000
Total project budget: $38,000,000
7
Project Budget
• Current $38M request is total cost for the project, offset by several sources
8
SCL contribution for system expansion ($3.0M)
Grant and State Funding ($4.9M)
Norwegian Cruise Line contribution in negotiation
Next Steps
• Final design and permitting complete: Q1, 2023
• Memorandum of Agreement with Seattle City Light on Roles and
Responsibilities and Cost Sharing: Q1, 2023
• Advertise major works contract Q1, 2023
• Shore Power Funding Agreement and Possible Lease Amendment with
Norwegian Cruise Line Holdings: Q2, 2023 (Separate Action)
• Onsite Construction, Testing & Commissioning: Q3, 2023 – Q2, 2024
9
Questions?
10