South Satellite Infrastructure Upgrade Project
Executive Summary
Internal Audit (IA) completed an audit of the South Satellite Infrastructure Upgrade Project
(SSIUP) for the period February 2019 through May 2022. The audit was performed to assure the
quality of the Port of Seattle’s (Port) monitoring of the SSIUP, to assess if it was meeting project
management standards, and to determine if change orders were allowable, properly approved,
and reasonable.
We selected this project based on the number of designer error and omission change orders
(COs), and the removal of critical milestones as reflected in the original contract. Our sample for
testing included the largest dollar value change orders, ones that changed the scope of the
project, and those that were the result of errors and omissions.
The SSIUP is approximately 45 years old and was in need of complete renovation. The SSIUP
serves a mix of domestic and international carriers and will continue to be a critical terminal asset
for Seattle-Tacoma International airport. The final construction estimate, performed by Port
Aviation Project Management (AVPM), totaled $32.98 million. In February 2019, the Port received
two bids for the project. The lowest bidder, James W. Fowler Co. (JWF), was awarded the contract
in the amount of $28.36 million.
The project delivery method was a design-bid-build with a lumpsum contract. The total
construction cost as of September 28, 2022, was $31.09 million, which included approximately
$2.73 million in COs. The contract required that JWF substantially complete the work no later than
1,000 days following the contract execution date, which would have been November 28, 2021.
The actual substantial completion and physical completion were achieved on December 22, 2021,
and March 13, 2022, respectively. Construction Management (CM) provided a time impact
analysis submitted by JWF for the delay of 24 days to achieve substantial completion. As of
September 2022, a change order for the approved days has not yet been issued. Port CM is
currently reviewing the contractor’s support for some of the Force Account change orders, to
assure accurate payment to the contractor. They anticipate the final closeout of the project by
December 2022.
In general, Port management’s monitoring aligned with the Port’s policies and procedures. We
would like to extend our appreciation to the SSIUP Project team and staff at JWF, for their
assistance and timely responses to our requests.
We identified an opportunity where internal controls can be enhanced or developed. This
opportunity is listed below and discussed in more detail, beginning on page six of this report.
(Low) We identified opportunities for Port management to strengthen controls over reconciliation
of Not to Exceed (NTE) COs. Additionally, we identified instances where SOPs were not followed.
Management has made corrections based on recommendations from prior audits, and these
should be reflected in future projects.
Glenn Fernandes, CPA
Director, Internal Audit
Responsible Management Team
Janice Zahn, Interim Chief Engineer and Director, Engineering Services