DATE: October 17, 2022
TO: Stephen P. Metruck, Executive Director
FROM: Eileen Francisco, Director, Aviation Project Management
Laurel Dunphy, Director, Aviation Operations
SUBJECT: Restroom Renovations Phase 5 Construction (CIP #800697)
Total estimated project cost:
ACTION REQUESTED
Request Commission authorization for the Executive Director to 1) advertise and award a major
works construction contract for the fifth phase of the Restroom Upgrades on Concourses B, C,
and D project at Seattle-Tacoma International Airport; 2) execute a Project Labor Agreement for
this project; and (3) use Port crews. The amount requested under this authorization is
$13,858,000 of an anticipated total project cost of $61,692,000.
EXECUTIVE SUMMARY
The public restrooms on Concourses B, C, and D, are old, outdated and overcrowded. When
complete the new restrooms created by this project will improve the passenger experience by
being brightly lit, featuring touch free faucets, soap dispensers and paper towel dispensers, and
larger, more accessible stalls.
This is a five-phase project. The first three phases are complete, Phase 4 restroom construction
is nearing completion. This request is to construct the Phase 5 restrooms. Phase 5 will remodel
the remaining public restrooms on Concourses B, C and D and will incorporate adult changing
tables, nursing suite, service animal relief area and additional family restrooms. This project was
recently awarded a $10,000,000 grant from the Federal Aviation Administration (FAA) through
the Bipartisan Infrastructure Law (BIL) — Airport Terminal Program (ATP). Project Labor
Agreements (PLAs) have been used on past projects to reduce risk to operations impacts and
construction schedule delays caused by potential labor disputes. This project is planning to use a
project specific PLA which is awaiting approval by the FAA.