Part 150 Overview
Code of Federal Regulations 14 (CFR 14) Part 150 FAA established
study guidelines
Airports must follow those guidelines to obtain FAA Airport
Improvement Program (AIP) grant funding for abatement and mitigation
projects
Part 150s focus on airport noise and land use incompatibilities within
the 65 Day/Night Level (DNL) contour
Updated 65 DNL noise contours are the required outcome of a Part 150
FAA-approved mitigation measures become eligible for AIP funding at
80%
DNL Noise Contour
Day Night Level (DNL) annual average of noise from aircraft operating at SEA
Contours must be produced using the FAA-required Aircraft Environmental Design
Tool (AEDT)
65 DNL is the FAA-required metric and level
Contours are depictions of the cumulative impacts of aircraft noise, and must be
reviewed and approved by the FAA
FAA will not allow the use of noise monitoring data to assess impacts
The 65 DNL contour is the basis for land use analysis in the Part 150
Current and future noise impacts will be assessed
3
SEA 2018 DNL Contour
4
S 240th St
S 100th St
Part 150 Land Use Planning
Identify noise incompatibilities within surrounding communities - below
65 DNL is compatible with all uses
Incompatible land uses at or above 65 DNL:
Residential
Schools
Places of worship
Hospitals
Nursing homes
Daycare facilities with licensed educators
Evaluate new potential noise abatement initiatives
Evaluate ongoing programs from past Part 150 Studies
5
SEA Part 150 Studies
Initial study completed in
1985
Updates
1992
2002
2014
Extensive public
involvement
6
2014 Part 150 Study Record of Approval
Noise Mitigation
Updated noise remedy boundary
Continuation of single-family sound
insulation
New Condominium sound insulation
New Apartment sound insulation
Continuation of School Sound
Insulation Program
Voluntary acquisition of residential in 3
rd
runway South Approach Transition Zone
(ATZ)
7
2014 Part 150 Study Record of Approval
Noise Abatement
Continuation of Aircraft Maintenance
Run-up restrictions
Continuation of the Fly Quiet Program
including monitoring noise abatement
procedures in place
8
Ongoing monitoring of the Noise Abatement Corridors
Evaluate and Upgrade the Noise Monitoring System
Continue to operate the Noise Programs Office
New SEA Part 150 Study Update
Consulting firm will be hired to lead the study and provide
technical expertise
Finalizing the initial consultant scope
Detailed project scope will be developed with chosen consultant and
presented to the Commission for input
Consultant procurement finalized by mid year 2023
Study development and data collection late 2023
Full public study outreach anticipated early 2024
Multi-year study that may take 4-7 years to complete
9
Commission Project Authorization
November 8
th
$1M authorized in 2022
$6M this request to fully fund the project
Authorization to procure consultant and execute contract
10