JUSTIFICATION
The South Concourse Evolution project has completed the Project Definition Document (PDD)
and has reached a design milestone of approximately 15% design. The team is ready to
assemble its full delivery team and to begin full design and execute the project. This
commission action will provide the authorization and funding necessary to progress the project
to approximately the 90% design level, at which time the Maximum Allowable Construction
Contract value will be determined. The project team will return in the future for further
authorizations outside of and beyond this authorization.
Project Delivery Selection:
The team has selected an alternate delivery method, GC/CM, for this project. The project team
met with stakeholders and analyzed multiple delivery methods and has selected GC/CM as it
has proven to be an effective and successful delivery process for the Port as well as other public
agencies. This delivery process partners with the designer and the general contractor while
allowing the Port to maintain separate contracts throughout the design and construction of the
project. Staff are currently developing and preparing to begin procurements for the project
management, design, commissioning, and GC/CM contractor teams to kick-off the design
phase, a collaborative effort.
General Contractor/Construction Management Project Specific Contract:
The GC/CM delivery method will allow for the contractor to be part of the complex design and
intricate construction phasing and sequence development that will minimize risk to airport
operations, provide the highest level of customer service during construction, and gain earlier
insight to and control of construction costs. The GC/CM is anticipated to aid the team with
construction techniques, validating the schedule phasing and sequencing, and preparing
subcontract packages for the MACC.
Project Management Project Specific Contract:
The team is anticipating hiring an external project management firm with expertise in using the
GC/CM delivery method and with projects of this scope and complexity. The contract will
include a project specific ATR. ATR’s have played a critical role in successfully delivering
previous mega projects and are recommended to represent the 25 airline carriers that utilize
the South Concourse. The project would benefit from having a project specific ATR contract
through the life of the project to serve as a liaison between the project and Airlines. Having a
dedicated ATR engaged through the life of the project is critical to the success of delivering the
project in such ways as decision making, communications, and implementation of plans.
Construction Manager Project Specific Contract:
The team plans to bring on board a CM firm that has expertise using the GC/CM delivery
method and with projects of this scope and complexity. The firm will assist staff in executing
the project from reviewing bid packages, negotiations on schedule and budget for MACC and
other bid packages necessary to construct the project, responding to contractor