
COMMISSION AGENDA – Action Item No. __8d__ Page 4 of 6
Meeting Date: October 11, 2022
Template revised June 27, 2019 (Diversity in Contracting).
year it is delayed. Current maintenance has been minimal, and the equipment cannot be safely
worked on by Port Electricians; therefore, costs to maintain are not included.
Pros:
(1) Lower initial capital cost.
Cons:
(1) The equipment cannot currently be serviced safely.
(2) The equipment is already in a state of advanced disrepair due to the proximity to
saltwater and areas of stormwater intrusion.
(3) If the equipment fails, a long-term diesel generator will be required to provide power
to the tenants. This will impact air quality and cost significantly more over time, in large
part due to high fuel costs.
This is not the recommended alternative.
Alternative 2 – Phased approach: Replace switchboards one at a time as separate projects.
Cost Implications: $6M to $8M
Pros:
(1) Phases upfront capital costs for major electrical equipment over several fiscal years.
(2) Advances Century Agenda goals of investing in maritime industries.
Cons:
(1) Over time, this alternative will cost more due to piecemeal design costs, construction
escalation costs, piecemeal ordering of large electrical equipment, and mobilization of
construction crews for each separate project.
(2) This alternative will take much longer to implement due to phasing and long-lead times
for major electrical equipment (12-18 months). The individual projects would either
need to be overlapped, or the risk accepted that large gaps in equipment replacement
may result in existing equipment failure.
(3) This alternative would be difficult to implement due to the needed conduit and vault
system replacement resulting in complex logistics and planning.
(4) This alternative will require multiple planned power outages to switch over the new
equipment, rather than a single outage to switch over all the equipment at once.
This is not the recommended alternative.
Alternative 3 – Replace all electrical infrastructure as a single capital project to bring the
equipment up to National Electrical Code (NEC) standards and provide for a safe working
environment with reliable power to the MIC facilities.
Cost Implications: $6.4M (initial planning level estimate)
Pros:
(1) Advances Century Agenda goals and Maritime Division strategic goals.
(2) Upgrades and replaces degraded electrical infrastructure that is not safe to maintain
and does not meet current National Electrical Code (NEC) standards.