Procurement
Chiller 6 Repairs
Chiller 6
Controls
Tubes
Capacity: 1500 Tons
1 of 8 Chillers in CMP
Supplies 10% of SEA
Controls to be
upgraded as part of
F&I project.
All tubes must be
removed to provide
access to ruptured
ones
.
Item No. 8e_supp
Meeting Date: August 9
th
, 2022
Procurement
Chiller 6 Repairs
2
Flow Control Ruptured Tube
Looking East
Controls flow between
terminal and cooling
towers.
Internal tubes froze
and ruptured. These
must be replaced.
Unbolted cover of
Chiller 6
.
Item No. 8e_supp
Meeting Date: August 9
th
, 2022