
COMMISSION AGENDA – Action Item No. __8c__ Page 2 of 4
Meeting Date: August 9, 2022
Template revised June 27, 2019 (Diversity in Contracting).
Diversity in Contracting
The project is utilizing an existing Indefinite Delivery / Indefinite Quantity (IDIQ) contract to
provide design support services. The contract has an overall requirement for 10% WMBE
participation. Port Construction Services (PCS) will complete the construction portion and will
work with the Diversity in Contracting (DC) department to outreach to the WMBE community of
any small works opportunities.
DETAILS
The project is located at the south end of the departures drive. However, construction will impact
both the arrivals and departures drives.
This project was originally scoped to replace three existing expansion joints on the departures
drive. However, it became apparent that there was scope overlap with two adjacent projects:
C800862 Terminal Security Enhancements and C801204 SEA Gateway. After coordinating with
the two adjacent projects the scope of work for this project was reduced resulting in $600,000 in
savings. It was also identified that this project’s scope of work, the drainage piping, needed to
be completed prior to Terminal Security Enhancements’ installation of security bollards along the
arrivals curbside that is planned to start this fall.
Additionally, the project carried additional contingency related to potholing work necessary to
proof the conceptual design. This work has now been conducted, the conceptual design was
proven, and the additional contingency has been removed from the project.
Scope of Work
This project will correct a failure of the existing storm drainage facilities at the south end of the
departures drive.
(1) Remove and replace an existing catch basin on the departures drive.
(2) Install new storm drainage piping under the departures drive, down an existing column
and across the arrivals drive to an existing catch basin.
(3) Replace one existing expansion joint seal on the departures drive.
(4) Repave the existing departures drive shoulder and reseal the structure joint to direct
stormwater flow into the new catch basin.
(5) Remove and replace a small section of existing storm drainage pipe that has deformed.
Schedule