
COMMISSION AGENDA – Action Item No. _8f___ Page 2 of 6
Meeting Date: July 26, 2022
Template revised June 27, 2019 (Diversity in Contracting).
Program Budget Update
The original project was estimated at $340 million. Since that original budget was established,
project cost risk has increased and the estimates for the project have grown. The main drivers
of the increased estimates are additional sustainability scope, baggage transfer line impacts,
and contractor estimates reflecting escalation due to COVID and the current geopolitical
situation.
To manage costs and scope the project has taken several steps. Between concept and 15%
design the Port, the contractor, and the design team met every two weeks to value engineer
and right size the project scope. That effort led to a $20 million reduction to the concept
estimate. That right-sized scope and project programming was used to develop a 30% design.
The 30% design was again estimated, and the estimates were reviewed and reconciled with the
Port, the designer, and the contractor.
The design is currently moving from 30% development to 60% development and the project
team holds weekly Target Value Design meetings. At these meetings the project team meets to
review specific cost savings ideas. Cost savings that do not violate Port design standards or the
project program are incorporated into the design.
As the design develops, the project teams will continue to assess potential savings in real time
with the design team and the contractor. While this will not prevent the higher cost of
delivering the project, it will be a tool to control the cost increases and ensure that the scope of
work is appropriate to the needs of SEA.
Estimate Trends
Sustainability Initiatives: $10.4M
Non-Discretionary Scope Changes: $24M
Escalation and Scope Definition: $32.6M
Current Estimate Range: $340M – $420M
The available Program Contingency is $14.5M. The project team is assessing how much of this
contingency can be allocated to the existing budget. The team is working to balance known
risks against the available funds.
JUSTIFICATION
Early work packages allow the project to accelerate specific scopes of work that will benefit the
project schedule. Staff worked with the design team and the General Contractor Construction
Manager (GCCM) to identify scopes of work that could be accelerated without causing
excessive risk to the project. The three major scopes of work that this request represents are
the structural steel, vertical circulation, and the exterior curtain wall.