COMMISSION AGENDA – Action Item No. 8d Page 2 of 2
Meeting Date: July 26, 2022
Template revised September 22, 2016; format updates October 19, 2016.
• Soft cost increases (Consultant + In-house Staff) due to the longer anticipated project
schedule,
• Work slowdown and rescheduling of activities on cruise and BHICC event days.
• 5-to-10-week delay for roof repairs, painting and various upgrades.
This request is to keep the project from being encumbered.
Additionally, the following are more reasons for the request.
• Liquidated Damages are being issued to the contractor for the late delivery; however, it
will still take time to offset the current costs after July.
• Scheduled events at the facility required mobilization and demobilizations in certain areas
of the site to occur.
• Staff noticed the project schedule has been slipping (beyond our previous anticipated
February 14th completion date).
The Pier 66 campus consists of Anthony’s Restaurant, the Bell Harbor International Conference
Center and the Bell Street Cruise Terminal. The campus roofing system is highly complex,
consisting of 12 separate roof surfaces and 4 different roofing systems. Dating back to 1995, the
original roof is now twenty-seven years old and required comprehensive maintenance and
repairs to extend its service life.
The project will now be complete in Q3/2022 with Closeout in Q2/2023.
There are no attachments to this memo.
PREVIOUS COMMISSION ACTIONS OR BRIEFINGS
June 22, 2021 – Irregular Bid and additional funding request
March 23, 2021 – Construction funding authorization
December 15, 2020 – Design funding authorization