Template revised April 12, 2018.
COMMISSION
DATE: June 16, 2022
TO: Stephen P. Metruck, Executive Director
FROM: Susie Archuleta, Sr. Real Estate Manager
Rod Jackson, Capital Project Manager
Melinda Miller, Director, Portfolio and Asset Management
SUBJECT: WTCW Roof Replacement – Irregular Bid (CIP #801104) (Short Form)
Total estimated project cost:
ACTION REQUESTED
Request Commission authorization for the Executive Director to award and execute a
construction contract to the third low bidder for the WTCW Roof Replacement project due to an
irregular bid outcome for the three bids submitted, and to increase the project budget in the
amount of $220,000 to fund the irregular bid outcome.
The amount of this request is $220,000 for a total estimated project cost not to exceed
$2,435,000.
SUMMARY
This request is for authorization to proceed with awarding and executing a construction contract
on an irregular bid as required by Resolution No. 3605 (as amended by Resolution No. 3628)
Paragraph 4.2.3.4. Three bids were received in response to the construction advertisement. The
first low bidder was deemed non-responsible. Additionally, the second low bid came in at 12.36%
over the engineer’s estimate, which qualifies the lowest responsible bid as irregular. The bid
received was $1,400,000 which is $154,000 over the engineers estimate of $1,246,000. The
additional funds requested in this action will be used to cover the difference of the bid amount
and to ensure funds are available for project contingency and taxes.
The recommendation is to accept the second highest bid. The bidder (Snyder Roofing of WA) is
a certified Prime Contractor. Acceptance of this bid would meet the project goal of 5% WMBE
participation.
The project scope has been value engineered during the planning and design process to balance
the WTCW Roofing project needs for daily operation versus the longevity of the system. Rejecting