
Template revised September 22, 2016.
COMMISSION
DATE: June 14, 2022
TO: Stephen P. Metruck, Executive Director
FROM: Tina Soike, Director Engineering Services
Janice Zahn, Assistant Director Engineering, Construction Services
SUBJECT: WTCW HVAC Replacement (CIP: C800199) 60 Days
ACTION REQUESTED
Request Commission authorization for the Executive Director to execute a change order to
Contract MC-0320086 World Trade Center West HVAC Replacement Project to add up to 100
Calendar days to the Contract Duration to reconcile the contractual completion date to the actual
completion date.
EXECUTIVE SUMMARY
This change order requires the addition of up to 100 calendar days to the Contract Duration.
Commission action is required under the General Delegation of Authority because the Change
Order includes a time extension of more than 60 days. No additional project funding is included
with this request.
Description of Change Order
This change order revises the contract completion date due to supply chain impacts to the project
schedule.
Background
This project at the WTCW building will provide an energy efficient and sustainable replacement
for the building’s existing 22-year-old mechanical system.
On January 22, 2021, the Port executed a construction contract with Johansen Mechanical, Inc.
in the amount of $2,798,000. The Contract has experienced some cost and schedule growth due
to unidentified conditions in the Basis of Design which have extended the current Contract
completion date by 36 days to April 8, 2022. On 1/19/22, the Port executed Change Order #02
which directed the contractor to upgrade the current fire alarm system. This was a discretionary
change added to the scope of this project to minimize future (and greater) impacts to the Central
Waterfront Elevator Upgrade Project which would require the upgraded system in order to
complete work at the Bell Street Elevator. As a part of upgrading the current HVAC system, fire
alarm work was required so rather than have the HVAC project complete it’s work only to be
undone immediately afterward by the Elevator project, the scope to upgrade the alarm panel