Shilshole Bay Marina:
X Dock Rehabilitation
Commission Meeting | May 10, 2022
Kenneth R. Lyles Director of Maritime Operations and Security
Darrel Dare Senior Manager, Recreational Boating
Julie Yun Capital Project Manager
Mark Longridge Capital Project Manager
Item No.: 8e_Supp
Date: May 10, 2022
Agenda
1. Commission Request
2. Project Context
3. Alternatives Considered
4. Timeline
5. Questions
2
X Dock
Fixed Pier
Action Requested
Request Commission Authorization from the Executive Director to:
Request Commission authorization for the Executive Director to advertise
and execute a major public works construction contract for the Shilshole
Bay Marina X-Dock Rehabilitation in the amount of $1,200,000 (total
authorization $1,650,000).
3
Project Context: Location
4
X Dock
Fixed Pier
North Dry
Storage
Shilshole Bay Marina
X Dock at Shilshole Bay Marina
Project Context: Current Condition
5
Project context: Scope
Supporting Structure (“Substructure”)
Replace 20 existing creosote timber piles
with 13 steel piles utilizing waterside
crane barges to minimize construction
impacts.
Superstructure (not in scope)
Retain superstructure for the remainder
of its service life.
6
X Dock
Fixed Pier
North Dry
Storage
Alternatives Considered
Alternative 1: No/delayed action (Not Recommended)
Cost Implications: Reduced cost for avoiding work but potential for increased maintenance cost related to more
advanced repair needs in the future.
Pros: 1. Preserve Port capital funding and resources for other priority projects and financial initiatives.
Cons: 1. Potential integrity risk to the overall pier structure due to continued deterioration.
2. Potential commercial/financial risk due unplanned maintenance and implementation of load restrictions to
facility operations.
Alternative 2: Proceed with current design (Recommended)
Cost Implications: Allocation of $1,200,000 in the Capital Plan.
Pros: 1. Address deterioration of the supporting structure.
2. Improved service life with steel piles, as compared to the existing timber piles.
3. Replace creosote timber piles with more environmentally-friendly steel piles.
Cons: 1. Higher upfront capital cost.
2. Limited temporary construction impacts.
7
Project Timeline
8
Activity Date
Commission Design Authorization (complete) January 2021
Commission Construction Authorization May 2022
Design and Permitting Complete May 2022
Advertise Construction June 2022
Construction Start October 2022
In-use date March 2023
Questions?
9