
COMMISSION AGENDA – Action Item No. 8e Page 2 of 5
Meeting Date: May 10, 2022
Template revised June 27, 2019 (Diversity in Contracting).
ongoing commitment to the environment by removing approximately 1,161 treated timber
pilings and replacing them with steel pile systems over the past decade.
This project is designed to replace the piles and retain the existing superstructure under the
Port’s Pile Systems Repair & Maintenance Programmatic permit, substantially shortening the
local, state, and federal permitting time required for the work. The construction permit for this
project has been submitted to the City of Seattle SDCI and is currently under review.
JUSTIFICATION
The jib cranes and fixed pier are used by the over 80 north-end dry storage tenants launching
vessels, seasonal racing fleets participating in races hosted at the marina, and the public renting
the jib crane. Rehabilitation of the structure will allow long-term continued use of the jib cranes
for water access and maintain the viability of the facility.
Over the past decade, the Port has replaced aging treated timber systems at many of its facilities
as they reach the end of their service life. Most of these treated timber systems have been
replaced with steel systems that are longer lasting, more environmentally friendly, and stronger
than treated timber systems. Of the total piles removed Port-wide from 2011 to 2021 under the
Pile Systems Repair and Maintenance Programmatic permit, over 95% (1,161) were creosote- or
ACZA-treated timber pilings; nearly all pilings replaced under this program were replaced with
steel pile systems.
The current fixed pier structure is supported by the original 20 creosote timber piles which are
now reaching the end of their service life. Several have been previously repaired or show section
loss and deterioration. By replacing this support system with 13 steel piles, we will reduce the
total number of piles, improve environmental conditions, and provide a significantly increased
service life of over 30 years. The current superstructure and decking are in good condition and
will be retained to utilize its full-service life. The supporting structure has been designed to be
compatible with the eventual rehabilitation of the superstructure.
Diversity in Contracting
There is a 10% aspirational goal for WMBE utilization for the construction contract. The nature
of this work lends itself to an all-or-nothing WMBE utilization, as this work is likely to be
performed entirely by the general contractor.
DETAILS
Scope of Work
This project will replace the 20 existing creosote timber support piles with 13 galvanized steel
piles and frame system to support the existing wooden superstructure.