C Concourse Expansion
Budget Transfer and PLA
April 26, 2022
Item No. 8n_supp
Meeting Date: April 26, 2022
C Concourse Expansion
2
• Project Purpose
– Add four floors to the existing C1
Building
– Increase Airport Dining and Retail
offerings
– Increase leasable office space
– Increase airline lounge capacity
– Increase C3 holdroom size
– Add passenger amenities
(restrooms, meditation room,
nursing rooms)
• Budget Authorization and
Transfer Purpose
– Maintain airline access to baggage transfer
lines during construction
– Build permanent baggage transfer input
locations that will serve the airlines after
construction
– Baggage equipment requires special
knowledge to design and install. Baggage
Optimization Project has the expertise.
C Concourse Expansion
3
C Concourse Expansion
• Schedule Milestones
– Q2 2022 Enabling Construction start
– Q3 2022 60% Design submitted for review
– Q1 2023 90% Design submitted for review
– Q2 2023 Construction start
– Q1 2026 Early Completion
– Q2 2027 Late Completion
4