COMMISSION AGENDA – Action Item No. __8n__ Page 2 of 6
Meeting Date: April 26, 2022
Template revised June 27, 2019 (Diversity in Contracting).
JUSTIFICATION
The baggage system is a complicated system that requires specialized experience to design,
construct, and operate. Outages or impacts to one part of the system can have airport wide
effects. Because of the complexity and interdependency, the C Concourse Expansion project
has been working with the Baggage Optimization team to coordinate the relocation and
phasing of transfer lines that are inside of the CCE construction footprint. During these
partnering sessions it was determined that the most efficient way of executing the transfer line
relocations is for the BOP team to manage this scope of work.
The Baggage Optimization Project has the expertise required to execute this work expeditiously
with minimal disruptions to the larger baggage system. Transferring this scope and budget
would enable the CCE team to start enabling work in Quarter 2 of 2022 since the BOP team
would be able to leverage their knowledge and resources to remove and relocate transfer lines
much more quickly than the CCE team can accomplish.
The funds to be transferred are over and above what was originally estimated and scoped. The
original scope of the CCE project was to relocate exiting transfer lines and open them for use at
the end of the project. Since the project was initially conceived, the transfer line requirements
have changed. The project will now provide at least one transfer line for use by the airlines for
the duration of the project. This will necessitate complicated phasing and the demolition and
rebuilding of portions of the transfer lines multiple times. Because of this, the project will be
utilizing approximately two thirds of the program contingency to cover the additional cost. At a
later date, the project team may return to Commission to authorize a budget increase that will
replenish the program contingency.
Diversity in Contracting
Baggage Optimization Phase 2 has a WMBE goal of 2%. This is due to the nature of the scope of
work primarily being baggage conveyors and limited building work.
DETAILS
The preliminary scope of work to be executed by the Baggage Optimization Project includes:
(1) Temporary removal of the C94 transfer line
(2) Temporary reinstall of the C94 transfer line
(3) Permanent removal of the TX7 transfer line
(4) Design and construction of a new D1 transfer line
(5) Feasibility review, design and construction of a new permanent C94 configuration
Schedule
The following schedule represents the overall C Concourse Expansion Project: