COMMISSION AGENDA – Action Item No. __8k__ Page 6 of 7
Meeting Date: April 26, 2022
Template revised June 27, 2019 (Diversity in Contracting).
April 10, 2012 – Authorizations for the North Sea-Tac Airport Renovations program for: 1)
preliminary project funding; 2) execution of consulting contracts for design/construction
support services and project management services; and 3) use of Port crews and
consultants to conduct regulated materials management surveys and field support
services for preliminary project planning tasks.
North Satellite Renovation & North Satellite Transit Station Lobbies (CIP #C800556)
March 10, 2020 – The Commission authorized
increase the North Satellite Modernization Project budget by $40,000,000 ($32 million
capital and $8 million expense) for a total project authorization of $712,125,232.
August 15, 2017 – The Commission authorized
Increase the authorized budget by $107,000,000 capital and $500,000 expense and
authorize the remaining $261,547,392 capital and $8,800,000 expense, amending the
Hensel Phelps (HP) contract by $161,563,526 for the final MACC to complete the project
in Q3 2021. Authorize execution of all pending and future change orders to the HP
contract within the authorized budget and project scope to avoid potential delays.
Authorize Port crews to support NSAT construction and authorize Port staff to enter
into a TRA with AS for the reimbursement of AS and Port responsible design efforts and
improvements.
June 27, 2017 – The Commission authorized four NSAT related items:
increase project authorization for the North Satellite Renovation & North Satellite
Transit Station Lobbies Project by $200,000,000; execute Preliminary Work Amendment
#3 (PWA #3) with Hensel Phelps (HP) for up to $200,000,000; authorize Port staff to
execute all change orders to the HP contract within authorized budget and project
scope without returning for additional Commission authorization; and authorize Port
Construction Services (PCS) to execute small works contracts and use Port crews to
support NSAT construction
September 13, 2016 – The Commission authorized four NSAT related items:
the increase of project scope and budget (capital) by $7,000,000 for the revised third
floor layout to better accommodate the signature restaurant, provide 3,000 additional
square feet of future airport related leasable space, and increase AS premium traveler
lounge as requested by 4,850 square feet.
Increase authorization by $1,000,000 for project design.
Amend design service agreements with AECOM that exceed 50% value of the original
contract.
Increase authorization by $30,000,000 to accommodate Preliminary Work Package #2
construction.
May 24, 2016 - The Commission authorized four NSAT related items:
Increase of project scope and budget (capital and expense) by $121,219,098 for 30% &
60% design scope additions and risk contingencies
Increased authorization of $11,000,000 for continued NorthSTAR Program/Project
Management services and NSAT design and overall project support.
Amend service agreements with Jacobs Project Management Co. and AECOM.