Project Risks
RISK DESCRIPTION PROBABILITY IMPACT MITIGATION PLAN
Project Coordination Project Construction schedule
tied to the Baggage Optimization
and C1 expansion projects
finishing utility and build-out
work at the Central Terminal
Ramp by fall 2022.
L M
Critical reviewers have been identified from
surrounding projects to reduce impacts and
overlap. Coordination meetings are ongoing.
Cost of Materials Unanticipated price fluctuation
of major equipment and
materials.
M M
Port authorized to issue 10-year compactor purchase
contract to mitigate sudden price
fluctuations. Escalation and material pricing updated
in latest design estimates.
Complex Construction Utility work will require removal
and replacement of airfield ramp
paving. Contractors unsure of all
risks in area.
M M
During Design extra validation time was allotted for
field surveys, potholing and designer onsite visits.
Work affecting Tenant
operations
Requires move of Tenant
Refrigeration units affecting
food/perishable storage.
M L
Working with ADR on timing and duration of
outages. Project will provide new condenser units
and pressure test the new assembly prior to cut
over. Alternative storage will be provided.