
COMMISSION AGENDA – Briefing Item No. 11c Page 4 of 6
Meeting Date: April 12, 2022
Template revised September 22, 2016.
Key Risks and Mitigation Strategies
1. Complex phasing: The C1 Building, where the expansion is to occur, is currently
occupied on all three existing levels. Throughout the life of the project, these levels will
be occupied to a greater or lesser extent at different times during construction. The
mitigation strategy employed to control this risk is the early procurement of the GCCM.
The GCCM will be a partner with the project team and designer in creating a viable
phasing plan and finding cost effective solutions to phasing challenges.
2. Operational constraints: The C1 Building is located at the intersection of Concourse C
and Concourse D. There is limited access for construction material laydown and the
construction equipment required to erect a new building. The project team employed
two different strategies to control this risk: early procurement of the GCCM and early
involvement of Airport Operations. The project team completed Safety Risk
Assessments that addressed safety and operational concerns both during construction
and in the final configuration of the building.
3. Transfer Line Capacity: Transfer lines are used to transfer baggage from one flight to
another. There are a limited number of these lines available for use. Since the project
was first conceived, the needs of our airline partners have changed. Changes to the
transfer lines add additional complexity to our phasing and operational constraints. We
will be mitigating this risk by transferring scope and funds to the Baggage Optimization
Program which is already in construction. That program is best suited to design,
contract, and manage this very specialized scope of work.
4. Tenant Buildouts: The majority of the new building will be leasable space. The interiors
of these spaces will be built by the various tenants that are procured by Properties and
ADR. To fully open the building and start generating revenue, the tenants will be
building out their spaces while the project team is constructing the base building. This
will require a high level of coordination between tenant procurement, design, and
construction. Properties and ADR will need to let prospective tenants know details
about each space. They need to understand square footage, utility capacity, and use
restrictions. The project will need to coordinate construction times and durations, lay
down areas for each tenant, material deliveries, and space commissioning. The project
is managing these risks with multiple efforts. The project, in conjunction with the design
team, will create a tenant handbook. The details for each space will be specified and
restrictions being driven by the base building will be listed. During design and
construction, each tenant will have a project manager assigned to them that will
shepherd them through the Port design and construction process.
Environmental Sustainability
CCE is the first Tier 3 project to go through the Port’s new Sustainable Evaluation Framework
process (Resolution 3768). The project team, in conjunction with internal Port experts from AV