Template revised April 12, 2018.
COMMISSION
DATE: February 25, 2022
TO: Stephen P. Metruck, Executive Director
FROM: Eileen Francisco, Interim Director Aviation Facilities and Capital Programs
Wayne Grotheer, Director, Aviation Project Management Group
SUBJECT: SCADA (Supervisory Control and Data Acquisition System) project (CIP #800699)
Puget Sound Energy contract Text
Total estimated project cost:
ACTION REQUESTED
Request Commission authorization for the Executive Director to amend and increase the Not-
to-Exceed amount of the Puget Sound Energy (PSE) Engineering Services and Construction
Agreement (ESCA) required for the SCADA Project (CIP #C800699) from $1,014,000 to
$1,200,000
SUMMARY
PSE successfully completed Bow Lake substation upgrades in the spring of 2021. This now
allows for safe automated switching between PSE’s electrical power grid and the Port’s recently
completed Alternate Utility Facility which is a backup power source. Unfortunately, during
PSE’s engineering and construction, PSE exceeded the not-to-exceed contract value and is
requesting an Amendment to the PSE ESCA to authorize an additional $186,000 in contract
value to bring the total authorized value to $1,200,000.
The cost overruns were due to the following:
• Additional testing of the newly wired components to allow for safe return to operation.
• COVID construction delays associated with safety protocols.
• Crew overtime to complete all the work in the Port’s desired spring 2021 outage window
PSE exceeded the not-to-exceed contract value and completed this project in good faith to keep
on schedule and avoid any additional operational risk exposure associated with processing a
contract change order. This project is closed out from PSE’s end and no additional charges are
anticipated above the new proposed not to exceed value. The project team consulted with
Port Legal on this and their recommendation was to pay the additional amount.